Programme archaeology as separate evidence, approval, fieldwork and reporting gates. A single fieldwork bar cannot show when an affected area may be released or when the planning condition can be discharged.

Prepared and maintained by Cambridge Development Archaeology for development teams working across Cambridge and Cambridgeshire.

Sources, review dates and corrections →

Last source review: .

Content updated: .

The next decision

Model approvals, site readiness, fieldwork release and reporting as separate dependencies. The applicable condition and agreed scheme—not a generic number of weeks—determine what evidence unlocks each next step.

An illustrative two-parcel programme

For a hypothetical development with roads in Parcel A and later housing in Parcel B, first obtain the required method approval and confirm access, services and contractor interfaces. Complete and record the agreed work in A; release it only on the scheme’s required confirmation, while B follows its own agreed investigation sequence. This example is a dependency model, not a promised duration or release arrangement.

Keep a separate reporting and archive track after site handover. Add contingency triggers for inaccessible areas, unexpected deposits, changed foundation levels and authority comments. Record which milestone moves and who authorises the revised scope.

For county-advised Cambridgeshire schemes, the council advises up to 20 working days for briefs including HER search and up to 20 working days for initial WSI review. Check the live advice and your submission status; neither allowance includes all fieldwork, revisions or final discharge.

Content updated .

Archaeology is a sequence of stages, not one activity

A realistic programme shows each stage separately, because each has a different duration and a different dependency. Lumping them into one line is why archaeology appears to overrun when in fact it was never planned.

  • Desk-based assessment — dependent on the scope, source availability and HER data turnaround
  • Geophysical survey — dependent on area, ground conditions, crop cover, method and reporting time
  • Written scheme of investigation and approval — a discrete approval step with the authority, not an internal task
  • Trial trenching — driven by metreage, plant availability and how much archaeology is present
  • Evaluation reporting — needed before mitigation can be agreed, and routinely omitted from programmes
  • Mitigation excavation — the largest variable, set by area and feature density
  • Post-excavation assessment, analysis and archive — completion gates depend on the condition and approved scheme

Dependencies that catch people out

The archaeological programme depends on things outside the archaeologist's control, and those dependencies need to appear on the programme as links, not assumptions.

  • Approval of the written scheme of investigation is a precondition to fieldwork, not a parallel task
  • Land access, ecology constraints and seasonal restrictions can close fieldwork windows entirely
  • Machine and staff availability is finite and regional; a four-week notice period is not a plan
  • Confirm the reporting and archive evidence required by the condition; fieldwork completion and final discharge are not interchangeable

How to programme it properly

Put archaeology in the enabling works window with its own stages, and phase mitigation so cleared areas are handed back progressively rather than at the end. Any phased release must be agreed in the scheme and supported by the required handover evidence.

Then hold a weekly interface with the archaeological contractor while fieldwork is live, reporting against an agreed baseline, so divergence appears as an early warning rather than as a missed handover date.

The honest answer on duration

Anyone quoting a duration for your site without the evaluation data and the approved scheme is guessing. What we will commit to is telling you at tender stage whether the window you have is deliverable — and saying so plainly if it is not, rather than agreeing and handing back a delay.

Approval and delivery gates to put in the programme

Approval and delivery gates to put in the programme
GateResponsible interfaceEvidence needed before the next step
Requirement and briefDeveloper / archaeological adviserCondition trigger, site brief and current impact plan
Method approvalAppointed archaeologist / authorityWritten approval of the required WSI before the affected works
MobilisationArchaeologist / principal contractorApproved method, access, services, plant and safe working arrangements
Fieldwork and phased releaseArchaeologist / contractor / adviserAgreed record of the areas completed and the handover confirmation required by the scheme
Reporting and dischargeArchaeologist / planning authorityAccepted reporting and the archive or publication evidence required by the actual condition

Project review

Need archaeology set against a live construction programme?

Send the condition or brief, current site plan and programme milestone. We will identify the archaeological stages, approval gates and information needed to programme the next decision properly.