Mitigation

Archaeological mitigation strategy and delivery

Once evaluation has defined what is present, mitigation determines how much of the site has to be excavated, in what order, and at what cost. The strategy is where the money is decided — not the fieldwork.

Stage
Post-evaluation, pre-construction
Methods
Targeted excavation, strip/map/sample, watching brief
Agreed with
Local authority archaeological advisor
Drives
Programme, cost and construction sequence

Strategy

Proportionate mitigation is negotiated, not assumed

A mitigation requirement is a professional judgement about significance and impact. Where the evidence supports a narrower scope, that case has to be made deliberately, with the evaluation data behind it.

  • Testing whether design change can preserve remains in situ and reduce the area requiring excavation
  • Focusing full excavation on the areas of genuine significance rather than the whole footprint
  • Applying lighter-touch methods where the evaluation shows low density or heavily truncated deposits
  • Setting realistic sampling and analysis levels at the outset, so post-excavation costs are known
  • Phasing the work to match plot release, infrastructure and enabling works
  • Agreeing the approach in writing with the authority before any mobilisation
  • Defining in advance how unexpected discoveries will be handled and priced
  • Building reporting and archive obligations into the programme rather than leaving them open

Methods

Mitigation methods and when each is appropriate

Targeted excavation
Full excavation of defined areas of significant archaeology identified at evaluation. The standard response where remains are substantial and cannot be avoided.
Strip, map and sample
Controlled topsoil removal across a wider area, rapid mapping of what is exposed, then sampling of features. Suited to sites with dispersed or uncertain remains.
Preservation in situ
Design-led avoidance through foundation solutions, raised levels or repositioned open space. Cheapest where it is achievable, but must be raised early.
Archaeological watching brief
Monitoring of groundworks by an archaeologist where the risk is low but not negligible. The lightest option, and rarely sufficient on high-potential sites.
Post-excavation
Assessment, specialist analysis, publication where required, and archive deposition. A real cost and duration that must sit in the programme.

Delivery

How mitigation is delivered on a live site

  1. 01

    Strategy and approval

    Mitigation strategy and Written Scheme of Investigation prepared, negotiated and approved before any plant is booked.

  2. 02

    Mobilisation

    Resourcing, plant, welfare and site access confirmed, and interface with the contractor's programme agreed.

  3. 03

    Fieldwork

    Excavation and recording to the approved scheme, with progress reported against the agreed programme and variations flagged as they arise.

  4. 04

    Reporting and discharge

    Post-excavation assessment and reporting, then submission of the evidence required to discharge the condition.

Common questions

Mitigation: common questions

What does archaeological mitigation actually mean?

Mitigation is the work agreed to offset the harm a development causes to buried archaeological remains. In practice that means either avoiding the remains through design, or recording them through excavation before they are destroyed. Most development-led mitigation in Cambridgeshire is recording rather than avoidance.

Can mitigation be reduced or avoided?

Sometimes, and it is always worth testing. Preservation in situ through foundation design, level changes, or moving open space onto the most significant area can reduce the recording requirement substantially. This only works if it is raised while the layout is still capable of changing.

Who decides what mitigation is required?

The local planning authority, advised by its archaeological advisor, sets the requirement and must accept the approach before it is implemented. Our role is to put forward a proportionate, evidence-based strategy and to agree it in writing before mobilisation.

Can mitigation be phased around construction?

Usually yes, and on large sites it should be. Mitigation can be split to follow plot release or infrastructure phasing, provided the phasing is agreed with the authority in the approved scheme rather than improvised on site.